Building an installation schedule

Ömer Faruk Süer · Senior Sales Manager · 3 min read · Last updated:

General view of the Yeniler Etiket stand during Eurasia Packaging 2025: a green brand fascia on a dark body, timber display niches and meeting tables.

Short answer

How do you build an installation schedule?

You build it backwards. The opening hour is fixed, so cleaning, furniture, graphics, power, structural assembly and freight are placed behind it in that order. Then mark which steps have to wait for the one before. Those dependent steps form the critical path: a day lost there hits the opening directly, while a day lost elsewhere can usually be absorbed.

The reasoning follows below, section by section

Sources