Installation and logistics · Main guide

Installation and dismantling: three days on site

Ömer Faruk Süer · Senior Sales Manager · 4 min read · Last updated:

Overall view of the Er Bakır stand at Interwire 2025, with a dark grey structural frame, timber-clad columns and rows of ceiling spotlights.

Short answer

How long does an exhibition stand build take?

A mid-sized custom stand is normally built on site in three days. Day one is floor marking, platform and load-bearing structure. Day two closes the wall surfaces and brings in power, lighting and graphics. Day three is furniture, product placement, cleaning and handover. The number of days changes with the stand type, the hall build-up schedule and the working hours the organiser allows; the order does not.

The reasoning follows below, section by section