Building a stand at Messe Frankfurt

Ömer Faruk Süer · Senior Sales Manager · 3 min read · Last updated:

Visualisation of the stand placed on the hall floor plan, showing the neighbouring plots and the corner position of the İBA Kimya stand.

Short answer

What is needed to build a stand at Messe Frankfurt?

First the approval file: stand drawings, structural and electrical information, contractor and personnel lists, and a rigging application where needed. These are submitted by the date given in the venue’s technical manual, and late submission can be chargeable. Second, certain trades must be ordered from the venue’s approved supplier; power, water and rigging often fall into that group. Third come the waste and material conditions. All of it varies by venue and edition, so confirm it from the current manual.

The reasoning follows below, section by section